Skip to main content
Wednesday, 28 Oct 2026
Topic Archive

#R.Dhuvaafaru

8 Stories filed
82% of R. Dhuvaafaru (phase 2) Road Development project completed
Business

82% of R. Dhuvaafaru (phase 2) Road Development project completed

Maldives Transport and Contracting Company (MTCC) has stated that 82% of R. Dhuvaafaru (phase 2) Road Development project has been completed. MTCC also updated on ongoing works stating that they have commenced asphalt works on 17,790 square meter of roads....

R. Dhuvaafaru Road Development Project progressing at a fast pace
Business

R. Dhuvaafaru Road Development Project progressing at a fast pace

Maldives Transport and Contracting Company (MTCC) has stated that the Road Development project of R. Dhuvaafaru (phase 2) is  progressing at a fast pace. MTCC also updated on ongoing works stating that cable junction, curbstone and pavement blocks casting w...

65% of R. Dhuvaafaru Road Development Project completed: MTCC
Business

65% of R. Dhuvaafaru Road Development Project completed: MTCC

Maldives Transport and Contracting Company (MTCC) has stated that 65% of the Road Development project of R. Dhuvaafaru (phase 2) has been completed.  MTCC also updated on ongoing works stating that they have completed subbase and subgrade works of carriagew...

50% of R. Dhuvaafaru Road Development Project completed: MTCC
Business

50% of R. Dhuvaafaru Road Development Project completed: MTCC

Maldives Transport and Contracting Company (MTCC) has stated that the 50% of the Road Development project of R. Dhuvaafaru (phase 2) is well underway. MTCC also updated on ongoing works stating that they commenced the subbase works on January 4, 2022. Un...

MWSC installed additional solar power system in R. Dhuvaafaru
Business

MWSC installed additional solar power system in R. Dhuvaafaru

Malé Water and Sewerage Company has installed an additional solar power system in R. Dhuvaafaru. The new system was also installed at the Operation Centre in Dhuvaafaru. A 48-kilowatt system was previously installed at the center. Renewable electricity gene...

R. Dhuvaafaru Land reclamation project completed : MTCC
News

R. Dhuvaafaru Land reclamation project completed : MTCC

Under R. Dhuvaafaru Land reclamation and shore protection project, 22.2 hectares of land reclamation has been completed. Land reclamation and shore protection of R. Dhuvaafaru was assigned to Maldives Transport and Contracting Company (MTCC) by the Ministry...