Maldives Transport and Contracting Company (MTCC) has stated that they have commenced Sh. Funadhoo Football Ground Subbase Project.
MTCC commenced subbase preparation works on February 12, 2024.
Project was awarded to the company by Ministry of Sports, Fitness, and Recreation has awarded Sh. Funadhoo Football Ground Subbase Project to Maldives Transport and Contracting Company (MTCC).
Under the project company has to carry out excavation of 2400 cubic meter sand for subbase preparation and 15,039 square meter subbase preparation and compaction.
The MVR 3.49 million project was awarded to the company by Ministry of Sports, Fitness, and Recreation to be completed in 90 days.
MTCC has been undertaking many development projects throughout the country including building roads, airports, land reclamation, shore protection, and harbours.