Maldives Transport and Contracting Company (MTCC) has stated that they have completed Sh. Feydhoo Harbour Development project.
Under the project to develop Sh. Feydhoo Harbour company carried dredging operations of 24,456 cubic meter, 9000 cubic meter channel dredging operations, construction of a 317 meter breakwater, a 110 meter revetment, a 280 meter quay wall. In addition, the installation of navigation lights and installation of streetlights, installation of 1782 square meter harbour pavement, a ramp, and mooring buoys were undertaken.
The project was contracted to MTCC by National Planning, Housing and Infrastructure with a budget of MVR 35.67 million.
MTCC has been undertaking many development projects throughout the country including building roads, airports, land reclamation, shore protection, and harbors.