Maldives Transport and Contracting Company (MTCC) has stated that they have mobilized the site to commence Sh. Narudhoo Harbour Renovation Project.
Under the project to renovate Sh. Narudhoo Harbour MTCC has to dredge 36010 cubic meters from currently used harbour, dredging of 15202 cubic meter new harbour basin, channel dredging operations of 4120 cubic meter, construction of a 371 meter breakwater, a 205 meter revetment, and a 210 meter quay wall. In addition, installation of harbour lights, installation street lights, installation of 955 square meter harbor pavement and construction of a ramp.
The MVR 41.34 million project was awarded to the company to be completed within 365 days.