Maldives Transport and Contracting Company (MTCC) has stated that last shipment of rock boulders required for HDh. Nellaidhoo Shore Protection project has been delivered to project site.

MTCC also updated on ongoing works stating that 60% of revetment works are completed.

Under the project, the revetment of 870 meters of land will be carried out and a swimming area will be developed. The MVR 19.8 million project was awarded to MTCC to be completed within 250 days.

During the past three years, MTCC has completed several Harbour construction, land reclamation and Coastal Protection projects.