Maldives Transport and Contracting Company (MTCC) has stated that the third shipment of precast concrete blocks required for quay wall construction of HDh. Hanimaadhoo Harbor was delivered to the project site on November 17, 2021.

Under the project to develop Hanimaadhoo Harbour, MTCC has to dredge 53523cbm of harbour basin; also to dredge 31576cbm from currently used harbour basin; construction of a 355 meter breakwater; a 50 meter revetment; a 270 meter quay wall. In addition, the installation of navigation lights, installation of streetlights, and developing a 2583 square feet paved area will be undertaken.

The project has been contracted to MTCC with a budget of MVR 57.1 million.

MTCC has been undertaking many development projects throughout the country including building roads, airports, land reclamation, shore protection, and harbours.