Maldives Transport and Contracting Company (MTCC) has stated that the first shipment of rock boulders required for the breakwater construction of Sh. Bileffahi Harbor was delivered to the project site on September 28, 2021.

Under the project to develop Sh. Bileffahi Harbour company has to dredge 24125cbm of new harbour basin; construction of a 376m breakwater; 1150 square meter pavement; a 98m quay wall. In addition, the installation of navigation lights and installation of streetlights will be undertaken.

The project has been contracted to MTCC with a budget of MVR 28.42 million.