Maldives Transport and Contracting Company (MTCC) has stated that the first shipment of rock boulders required for the breakwater construction of Sh. Feydhoo Harbor was delivered to the project site on 4th September 2021. 

The company has also updated about the ongoing work stating that the new harbor basin dredging operations for the project is underway, and it is 97% completed.

Under the project to develop Sh. Feydhoo Harbour Company has to dredge 27500cbm of new harbour basin; construction of a 378m breakwater; a 90m revetment; a 276m quay wall. In addition, the installation of navigation lights and installation of streetlights will be undertaken.

The project has been contracted to MTCC by National Planning, Housing and Infrastructure with a budget of MVR 33.1 million.

MTCC has been undertaking many development projects throughout the country including building roads, airports and harbors.