Ha. Kela and HDh. Vaikaradhoo fish market projects have been assigned to the respective Councils of the islands and agreement concluded.
In addition, B. Fulhadhoo Council building construction project has been assigned to and agreement reached with Fulhadhoo council.
The agreements of these three projects was concluded between the three councils and Local Government Authority (LGA) on 3rd March 2021. Agreements were signed by CEO of LGA, Fathimath Afshan Latheef and Respective Island’s council president.
These projects are listed in the budget of LGA and will be carried out under Public Sector Investment Program (PSIP).
Cost of Kela fish market project is 2,815,320.04 while cost of Vaikaradhoo fish market project is 2,500,000. Furthermore, the cost of Fulhadhoo council building construction project is 3,500,000.