Work on Ha. Hoarafushi Football Ground Sub Base Preparation project is well underway, with overall 61 percent project progress stated Maldives Transport and Contracting Company (MTCC).
Currently, the company is working on Kerb stone laying, casting of drainage gutter top, subbase fill leveling and compaction works.
Under the scope of the project, MTCC is tasked with site clearing and compaction of 8,103sqm and excavating the required area. It also involves installing a soak pit.
Ministry of National Planning, Housing and Infrastructure contracted MTCC with the project on 11th September 2019.
Work on Ha. Hoarafushi Football Ground Sub Base Preparation project is well underway, with overall 61% project progress. Kerb stone laying, casting of drainage gutter top, subbase fill leveling and compaction works are currently ongoing. pic.twitter.com/4TGUA77XOy
— MTCC Plc (@MTCCPlc) September 6, 2020
The project is valued at MVR 2.53 million