Maldives Transport and Contracting Company (MTCC) has stated that the Land Reclamation under Sh. Komandoo Shore Protection Rectification and Mathi-Komandoo Connectivity Project has been completed.

MTCC also updated on ongoing works stating that 45% of Mathikomandooo Temporary Shore Protection and 52% of Komandoo existing revetment rectification works has been completed, Completing 50% of overall project.

Under the project, ratification of 1690 meter of shore protection rectification will be carried out, reclamation of 16.7 hectares of land in Mathi Komandoo, constructing a 1520 meter rock boulder revetment, 353 meter groynes and a 112 meter geobag revetment in the reclaimed area. In addition, construction of a 200 meter long link to connect the reclaimed area to Komandoo and Mathi Komandoo.

The project was awarded to MTCC for MVR 249.90 million to be completed within 730 days.