Maldives Transport and Contracting Company (MTCC) has stated that 90% of the Fehendhoo harbour has been completed.
The company has also updated about the ongoing work stating that the construction of Harbour Bridge is currently underway, and it is 91% completed.
Under the project to develop Fehendhoo’s Harbour, Company has to dredge 18500cbm of new harbour basin; 25000cbm of new entrance channel dredging; construction of a 214m quay wall; a 130m breakwater; and a 282m revetment. In addition, the installation of navigation lights, installation of streetlights and installation of 558sqm of paved area will also be undertaken.
https://twitter.com/MTCCPlc/status/1433623431933616128?s=19
The project has been contracted to MTCC under Work on Design and Build basis by Ministry of National Planning, Housing and Infrastructure with a budget of MVR 45.1 million.
90% of B. Fehendhoo Harbour development completed: MTCC
Maldives Transport and Contracting Company (MTCC) has stated that 90% of the Fehendhoo harbour has been completed. The company has also updated about the ongoing work stating that the construction of Harbour Bridge is currently underway, and it is 91% compl...
Discussion 0
Moderated