Land reclamation and Shore Protection Project for HDh. Makunudhoo Airport has commenced.

At a ceremony held at the Planning Ministry, the Government handed over the project to Big Fish Maldives Private Limited on June 23, 2023. A total of 43.12 hectares of land will be reclaimed and 3,943 meters of revetment will be constructed under the project.

According to Big Fish Maldives, they have started the project and the pace at which the project is being carried out, it is expected that the project will be completed before the deadline. The company expects the project to be completed by April next year.

The MVR 245 million (USD 16 million) project was awarded to the company to be completed in 366 days.