Maldives Transport and Contracting Company (MTCC) has stated that 72% of dredging operations has been completed under Ha. Hoarafushi Airport Jetty Construction Project.

MTCC also updated ongoing works stating that project is going at a fast pace. 

Company commenced Ha. Hoarafushi Airport Jetty Construction Project on September 7, 2022.

Under the project channel dredging operations of 18,000 cubic meter, construction of jetty using precast L blocks, construction of a geobag revetment and installation of navigational lights will be undertaken.

The value of the project is MVR 5.99 million.