Maldives Transport and Contracting Company (MTCC) has stated that 93% of Hanimaadhoo Harbour Development project has been completed.
MTCC also updated on ongoing works stating that 78% of payment works and 90% of sand-filled breakwater variation work has been completed and underway.
Under the project to develop Hanimaadhoo Harbour MTCC has to dredge 53523 cubic meter of harbour basin, dredging of 31576 cubic meter from currently used harbour basin, construction of a 355 meter breakwater, a 50 meter revetment, and a 270 meter quay wall. In addition, the installation of navigation lights, installation of streetlights, and developing a 2583 square feet paved area will be undertaken.
Hdh. Hanimaadhoo Harbor Development Project is well under way, with overall project progress of 93%. Harbour pavement works are ongoing with 78% completion, while the sald-filled breakwater vairation work has reached 90% completion.#MTCCProjects #RayyithungeKunfuni pic.twitter.com/vxKvPOc3OR
— MTCC Plc (@MTCCPlc) August 22, 2022
The project is worth MVR 64.6 million.