Maldives Transport and Contracting Company (MTCC) has stated 41% of the Nellaidhoo Shore Protection project has been completed.

MTCC also updated on ongoing works stating that 30% of the revetment works has been completed and project is progressing at fast pace.

Under the project, the revetment of 870 meters of land will be carried out. The MVR 19.8 million project was awarded to MTCC to be completed within 250 days.

During the past three years, MTCC has completed several Harbour construction, land reclamation and Coastal Protection projects.