Maldives Transport and Contracting Company (MTCC) has stated that 62% of Sh. Foakaidhoo Harbour Development project has been completed.
MTCC also updated on the ongoing work stating that the fourth shipment of precast concrete blocks required for the quay wall construction has been delivered to the project site.
Under the project to develop Foakaidhoo Harbour, the company has to dredge 45795 cubic meters of new harbour basin, construction of a 464 meter quay wall, 507 meters breakwater, and a 100m revetment. In addition, the installation of navigation lights, installation of streetlights and construction of 2320 square meter of paved area will also be undertaken.
Work on design and build of Sh. Foakaidhoo Harbor Development Project is well underway, with overall 62% project progress. Fourth shipment of precast concrete blocks required for quay wall construction have been delivered to project site on 15th April 2022.#MTCCProjects pic.twitter.com/IIAAwJ3pX7
— MTCC Plc (@MTCCPlc) April 19, 2022
The project is worth MVR 64.6 million.
MTCC has been undertaking many development projects throughout the country including building roads, airports, land reclamation, shore protection, and harbors.