Maldives Transport and Contracting Company (MTCC) stated that 91% of Nellaidhoo Harbor development project is completed.

The company has also updated about the ongoing work stating that the construction of breakwater is ongoing with 84% completion.

Under the project company has to dredge 62,863 cubic meters, 204 meters of inward barrier, 331 meters of outward barrier, 50 meters or revetment, 2,102 cubic meter outside pavement near the harbor is also to be developed including light posts of the roads and navigational masts.

The value of the project is MVR 50.8 million.