Ha.Muraidhoo harbour development project has been awarded to MTCC on design and build basis.
Muraidhoo Harbour construction project of MVR 33.7 million was contracted to MTCC by the Ministry of Planning, Housing and Infrastructure on 25th August 2021, allocating a completion period of 365 days.
ޑިޒައިން އެންޑް ބިލްޑް އުސޫލުން ހއ.މުރައިދޫ ބަނދަރު ހެދުމަށް @MTCCPlc އާ ހަވާލުކޮށްފި.
33,720,184.91 ރުފިޔާ އަށް ހަވާލުކޮށްފައިވާ މި މަޝްރޫޢަކީ 365 ދުވަހުގެ ތެރޭގައި ނިންމުމަށް ހަވާލުކޮށްފައިވާ މަޝްރޫޢެއް. pic.twitter.com/dbMWlpF2ss
— Min.of National Planning, Housing & Infrastructure (@MoNPHImv) August 25, 2021
As part of the project the MTCC have to dredge 29841 cubic meters of basin, 3546 cubic meters of entrance channel, along with construction of Groin, Breakwater, Quay walls, a walkway bridge, and installation of Revetment.In addition, interlocking Pavement near the harbor is also to be developed including light posts of the roads and navigational masts.