Maldives Transport and Contracting Company (MTCC) has stated that the Harbor development project of H.A Ihavandhoo is going smoothly at a fast pace. Second shipment of concrete blocks needed for quay wall has arrived recently.
Under this project, 30,509 cubic meters will be dredged and excavated and a quay wall spanning 95 meters will be built. A 284m breakwater and a 178m revetment will also be constructed.
Furthermore, installment of navigation lights and road pavement will be also completed by MTCC.
The second shipment of precast concrete blocks required for the construction of quay wall of Ha. Ihavandhoo Harbor have been delivered to the project site. The value of the project is MVR 48.5 million.#MTCCProjects pic.twitter.com/JLq7HBsMjQ
— MTCC Plc (@MTCCPlc) June 19, 2021
Ihavandhoo Harbor development project is evaluated to be worth 48.5 million Ruffiya.